County Road (CR) 209 Hardening Project Progress: 100%
Description: A half-mile of CR 209 will have wooden power line poles replaced with concrete power line poles and stronger cables that can withstand falling trees and tree limbs. This is to help mitigate the heavily wooded area of CR 209 in Green Cove Springs.
Budget: $300,000
Current Progress: Complete
Timeline: Completed end of December 2018.