Reynolds Water System Improvements

Reynolds Water System Improvements Progress: 95%

Description: Replace water lines to fire hydrants in Reynolds Park to increase fire protection in the area.

Budget: $1.37 million

Current Progress: This project has been fully designed and construction is estimated to start in early June. Project is estimated to be complete by January 2021.

Timeline: Estimated time of completion is January 2021.