Description
Second Phase of work for Public Works Admin Building and Compound, with the first phase of work completed in March 2020. Phase Two work includes building employee parking lot, reconfiguration of the drainage pond and installing associated drainage, and fence work.
Budget
$725,450 from Public Works CIP (Capital Improvement Project) Budget
Current Progress
Contract bid awarded to Thomas May Construction in March 2023. Construction anticipated to take four months.
Timeline
Anticipated to be complete in August 2023