Description
Construction of a boat dock for the police department marine unit as an extension of the Spring Park South Kayak Launch.
Budget
$600,000 total budgeted for Fiscal Year 2023/2024, with $300,000 as a Legislative Line Item Appropriation.
Current Progress
Design plan and permitting for construction is complete. Construction bid awarded to C&H Marine Construction in October 2023. Construction is anticipated to start January 2024 and be complete in March 2024.