Chapman Substation 3rd Feed

Chapman Substation 3rd Feed Progress

50%

Description: This project will provide a third feed, or third source of electricity, city-wide and increase capacity of available electricity for current customers and future growth. 

Budget: $4.5 million

Current Progress: Design is complete and construction contract awarded. City is starting bidding process for construction of new feeder and placing an order for a new transformer in July 2020. A transformer has been purchased and construction of the new feeder is 90% complete. City anticipates new feeder will be finished by January 31, 2021. 

For the Chapman Substation, the City is purchasing materials and finalizing the design. Construction began January 2021. City anticipates this project to be complete by July 2021

Timeline: Estimated time of completion is Fall/Winter 2021.