Harbor Road Advanced Wastewater Treatment Plant Construction (Phase 2)

Harbor Road Advanced Wastewater Treatment Plant Construction Progress

15%
 

Description: Plant improvements that will allow City to pump reclaimed water to residential areas of Green Cove Springs. This is Phase 2 of these improvement, which is the construction of a 1.25 million gallon per day - annual average daily flow - advanced wastewater treatment facility.
 

Budget: $18 million
 

Current Progress: City secured funding for Phase 2 of these improvements through the Florida Department of Environmental Protection State Revolving Fund. Design and permitting is also complete. This project is going out to bid in January 2021. Construction estimated to being March 2021. 
 

Timeline: Estimated time of completion is June 2022. Construction is estimated to last 12 months.