Third Feed to Magnolia Point
Third Feed to Magnolia Point Progress
Description: The city’s electric utility will be installing a third feed in the Magnolia Point area to better distribute electricity in the area, as well as provide alternate routes of electricity to the north end of the city. This additional feed will also help relieve the currently overloaded circuit in the two feeds in Magnolia Point.
Budget: $800,000
Current Progress: This project has been fully designed and permitted. City is securing funding for construction phase from FEMA.
Timeline: Estimated time of completion is December 2021.