Rookery Subdivision

Description

Installation of electrical infrastructure in the new Rookery Development.

Cost

TBD - contractor pays $2,600 per lot to the City for infrastructure costs.

Progress

The City has completed Phase 1 of the project, which included setting all transformers, pulling cable, and terminating connections. Also installed all secondary road crossings and connected them to secondary boxes in preparation for future home construction.

Phase 2A is now underway. This phase focuses on the main road through the subdivision, running from CR 15A to US 17. Work is currently about 50% complete. Work includes pulling six sets of cables along the main road—these will not only power the subdivision but also support an express feeder to US 17. The DR Horton contractor is nearing completion of the remaining conduit system, which will allow this work to continue.

Our team has worked closely with private electricians on site by opening transformers and secondary boxes so they could pull secondary cable to new homes that have passed final inspection.

Crews have begun pulling cable, setting transformers, and installing secondary cable to pedestal boxes along the subdivision’s side roads.

October update: Work on this phase is now nearly complete, with the contractor’s portion finished. This stage included pulling six sets of cables along the main road to supply power to the subdivision and establish an express feeder to US 17. Crews have now begun work on Section 2B, which involves pulling additional cable and setting transformers. Once that work is complete, we’ll return to terminate all transformers and splice boxes to wrap up the phase.

November and December update: Work on Phase 2B has been completed. This phase included the installation of 1/0 conductor to serve a sewer lift station and support future townhome development. Crews installed approximately 6,000 feet of cable, set multiple transformers, and completed all elbow terminations to energize the system. In addition, crews installed 2/0 URD secondary cable for a new streetlight circuit. Transformer terminations for the streetlights will be completed soon.

  1. 1 Phase 2 of Rookery Development - land cleared
  2. 2 Overpass in Rookery Development nearing completion
  3. 3 Phase 2 of Rookery Development - land cleared
  4. 4 Phase 2 of Rookery Development - land cleared
  5. 5 Phase 2 of Rookery Development - land cleared
  6. 6 Phase 2 of Rookery Development - land cleared
  7. 7 Phase 2 of Rookery Development - land cleared
  8. 8 Amenity Center in the Rookery development nearing completion
  9. 9 Lineman working on electric infrastructure for Rookery development
  10. 10 New electric infrastructure for Rookery development
  11. 11 New electric infrastructure for Rookery development
  12. 12 New electric infrastructure for Rookery development
  13. 13 New electric infrastructure for Rookery development
  14. 14 Electric bucket truck raised with lineman fixing a line
  15. 15 Electric bucket truck raised with lineman fixing a line
  16. 16 Public Works and Electric crews out installing a main feeder line pole in the front of the Rookery
  17. 17 Public Works and Electric crews out installing a main feeder line pole in the front of the Rookery
  18. 18 Public Works and Electric crews out installing a main feeder line pole in the front of the Rookery
  19. 19 Public Works and Electric crews out installing a main feeder line pole in the front of the Rookery
  20. 20 Public Works and Electric crews out installing a main feeder line pole in the front of the Rookery
  21. 21 Public Works and Electric crews out installing a main feeder line pole in the front of the Rookery
  22. 22 Rookery Development progress
  23. 23 Rookery Development progress
  24. 24 Rookery Development progress
  25. 25 Rookery Development progress
  26. 26 Electric wire being installed
  27. 27 Electric box being installed
  28. 28 Green Cove Springs Electric truck on site
  29. 29 Electric crew installing wire